Section 3: Wiring
04/12
27
51173 Rev. 8
LOAD CELL WIRING
Intalogix™ installations use a different numbering system for load cells because of
the digital addressing of the Smart Sectional Controllers (SSC).
Cell Numbering
With respect to the following starting position, face the platform from where the
indicator is located.
The cell at the upper left (far side) of the platform is
Cell One (1)
.
The cell positions along the far side are odd cell numbers,
The near side locations are even cell numbers.
Above is an example of four (4) section cell numberings using Smart Sectional Controllers
(
SSC).
Note:
Smart Sectional Controllers
(SSC) have terminals for two (2) Load
Cells, labeled
TB1
and
TB2
.
The odd numbered cell goes to
TB1
.
The even numbered cell goes to
TB2
.