SPP Pumps Split Case Pumps User Manual
Page 7

Pump Installation Guide
Manual No/Rev
W00-002E / 4
Our policy is one of continuous improvement and we reserve the right to alter specifications without giving notice.
Page 7 of 12
3.5 Slide Rail Mounting 
 
Close coupled pumpsets are supplied with 
the pump mounted directly on the motor. 
These motors may also be fitted with slide 
rails under the motor feet to permit 
withdrawal of the impeller from the casing 
without disconnecting the pipework. 
The motor, with or without slide rails, 
requires foundation support but where 
supplied, feet cast onto the pump housing 
must NOT be bolted down. It is, however 
recommended that the plinth extends under 
the pump to prevent accidental damage. 
 
Installation follows the same procedure as 
for pumpsets except for the alignment 
checks. 
Pump/driver
alignment
is
maintained
by
the
spigot/recess
construction of the pumpset and cannot be 
adjusted. 
 
3.6 
Vertical Pump Mountings 
 
Vertical pump are supplied with cast or 
fabricated motor stools. Mountings for 
fabricated pump stools are as shown for the 
channel section base frame, above. 
 
Cast pump stools are mounted typically 
thus 
 
SHIMS OR
PACKERS
FOUNDATION BOLT
CAST PUMP STOOL
CONCRETE
FOUNDATION
PLINTH
GROUT
FLAT WASHER
3.7
Installing the Pumpset 
 
It is important to install 
pumpsets 
BEFORE
installing the main suction and delivery 
pipework. This is to ensure that the pipes 
are positioned to match the pump location 
and do not transmit load and induce strain 
in the pump casing. 
For long coupled pumpsets, remove the 
coupling guard to provide access to the 
shaft and coupling. 
 
SLING FOR
CRANE LIFTING
COUPLING
GUARD
REMOVED
PLINTH
FLOOR
When using rag bolt fixing, suspend the 
pumpset over the plinth and hang the 
foundation bolts from their holes using 
tapered washers for channel base frames 
and plain washers for other types, with the 
nuts showing at least one full thread 
through. 
Place sufficient metal packing pieces on 
both sides of each foundation bolt hole to 
support the base frame at about 25mm 
above the plinth surface. Lower the 
pumpset and insert the rag bolts into their 
pockets. Continue lowering until the 
pumpset is supported by the packing. 
Adjust the height of the packing with shims 
in each position until the shaft is horizontal 
and the pump suction flange face is 
vertical, do not level from the baseplate as 
this may not be true to the shaft and 
flanges. 
 
Ensure that the foundation bolts are vertical 
to permit easy lifting of the pumpset, then 
grout in with non-shrinking grout. Allow 
sufficient time for the grout to harden, 
usually 24 hours or as recommended in the 
grout manufacturer's instructions. 
 
 
For chemical anchor fixing with channel 
section base frames it will be necessary to 
ATTENTION
