Getting started, Installation & setup – Magnum Venus Plastech PATRIOT Multi-Color Gel Coater MVG-PAT-1500XINT User Manual
Page 19

Patriot Multi-Color Operations Manual
Rev. 08/2012
Page | 19
Getting Started:
Installation & Setup
1.
Unpack unit & components
2.
Assemble frame work as needed (note drawing PAT-TA-400 or PAT-TA-600)
3.
Install the Carriage Assembly to the pump module assembly
4.
Install catalyst jug
5.
Install gel coat filter & surge chamber assembly
6.
Install air manifold and manifold air hose to power cylinder
7.
Attach hose fittings to gel coat pump, catalyst pump and gun air
8.
Attach pickup hoses to the inlet of the pump
9.
Internal Mix: Place flush tank in holder and attach air hose from manifold.
Connect yellow flush tube from gun to flush tank.
10. Double check all hose fittings and connections are tight
Air supply:
1.
Use minimum ½” air hose supply to the system. Air requirements: 18 CFM (510
L/Min.) at 90 -100psi (6
– 7bar)
2.
Open incoming air supply ball valve all the way.
Note: the main air supply ball valve is a safety ball valve and must be all the way
closed or all the way open. When the ball valve is closed the air pressure
remaining in the air manifold and air system will be released.
3.
Check that the system air is set at 90 to 100 psi.