Alpha Technologies UL LISTED User Manual
Page 8

Step 5
Sealing Rack Anchor Bolts
Coat each rack anchor bolt with Acid Resistant sealant before placement.
Insert anchor bolt through washer (Figure 5a). Run a bead of Acid-
Resistant sealant around rack footprint and anchor bolts. Lay 1/8”
Masonite sheet over the liner to protect liner from equipment and lifts. Set
the batteries in the rack (Figure 5b). Remove Masonite and duct tape.
Figure 5a Figure 5b
Step 6
Containment Layout
Lay out all “Eagle Barrier Walls” on the floor around the liner according to
the CAD assembly drawing (Figure 6). Assemble the wall components by
matching the labeled part numbers shown on the CAD drawing. For the
required configuration, use the slots on the adjustable components for
proper sizing. Use the Extrusion Clips to keep Barrier Walls in place
during installation. Barrier Walls should be at least 1” away from rack in
all directions. Using Barrier Wall components as a template mark the
location of the holes to be drilled in the floor. Remove the Extrusion from
the Barrier Walls. Remove the Barrier Walls carefully and note the
orientation of the components.
Figure
6
Page 7