Level 1 “New Installations”


A “new installation” is defined by EnviroGuard as a spill containment installation
where the battery rack has not yet been installed.


NOTES:

1. Installations Utilizing Pre-Fabricated Corrosion Resistant Liner
2. This Procedure is for New Installations ONLY.
3. The gray side of the liner must face up.


Step 1

Verify Measurements

Prior to starting the job, review the CAD drawing and compare it with the
actual kit. Verify measurements of the battery rack being used. If a
problem exists, contact the necessary management. (This procedure
should take place in the job walk; problems should have been identified
then, check the job walk checklist)


Step 2

Floor Preparation


Clean floor thoroughly of any debris that may interfere with a tight seal
between the floor and the spill containment barrier. Snap a chalk line
according to spill containment outside dimensions to identify exact
location. (Figure 1)

Note:
Spill containment barrier walls must be at least 1” away from rack,
VRLA stack or cabinet outside dimensions in all directions when job is
complete.











Figure 1