Run Time Table
Load
Run Time (Hours)
25%
23.4
100%
5.9
Table 1, Load to approximate run time.
2.0 Service Schedule
MAINTENANCE SCHEDULE
REGULAR SERVICE PERIOD
Note: Perform at every indicated
month or operating hour interval,
whichever comes first.
Each use
First month or 4–6
hrs.
Every 3 months or
50 hrs.
Every 6 months or
100 hrs.
Every year or
300 hrs.
Engine Oil
Check Level
O
Change
O
O
Air Cleaner
Check
O
Clean
O
2
Replace
O
1
Spark Plug
Check-adjust
O
Replace
O
Spark Arrester
Clean
O
Valve Clearance
Check-adjust
O
3
Fuel tank and filter
Clean
O
3
Fuel Line
Check
Every 2 years (Replace if necessary)
2
(1)–Replace the paper air filter element only.
(2)–Service more frequently when used in dusty areas.
(3)–These items should be serviced by an authorized AlphaGen dealer.
Table 2, Generator Component Service Schedule.
For commercial use, log hours of operation to determine proper maintenance intervals. Failure to follow this
maintenance schedule could result in non-warrantable damage.
NOTE:
5.
Move the choke lever to the START
position (Figure 4).
6.
Pull the starter grip lightly until
resistance is felt, then pull briskly out
until engine starts.
7.
Move the choke lever to the RUN
position after the engine warms up.
8.
Turn the output breaker to the ON
position, then verify output voltage on the
LCD display.
Figure 4, Choke Lever Location and Position Indicator
DCX
2000
36V DC GENERATOR
ALPHA
START
RUN
DCX
2000
36V DC GENERATOR
ALPHA
START
RUN
Figure 5, Turning Output Breaker On