5 operation test and installation instruction – Alpha Technologies Continuity: 6K_10K User Manual
Page 19
17
0170012-J0 Rev A
3.5 Operation Test and Installation Instruction
3.5.1 Start Up in Normal Mode
1. Open the terminal block cover on the rear panel (refer to Section 3.4). Make sure the grounding is
properly connected.
2. Make sure the utility breaker, UPS utility breaker, and Bypass breaker are in the Off position.
3. Make sure the utility voltage is within the allowable input voltage range of the UPS.
4. Connect the utility power separately to the terminal blocks of the UPS utility input and the bypass input.
5. Switch on the distribution panel breaker and the UPS utility and bypass input breakers.
6. The UPS starts up.
The green
and
LEDs illuminate indicating that the utility and bypass inputs are normal. The
LCD display, with parallel function, scrolls from Screen A1 to Screen B. Otherwise the LCD display scrolls
from Screen A2 to Screen B.
7. The UPS is in the bypass mode and automatically runs a self-test. If no fault messages appear, the pre-
startup of the UPS has been successful and the charger starts charging the batteries.
Screen A1
Screen A2
Screen B