OM-06628
SFV SERIES X‐PROOF PUMPS
TROUBLESHOOTING
PAGE D - 3
ELECTRICAL TESTING
Make the electrical checks which follow to deter
mine if pump malfunctions are being caused by
problems in the motor or in the power cable.
Test Equipment
A volt/amp/ohmmeter and megohmmeter of ade
quate range and quality are required to conduct
the electrical tests which follow. Use commercially
available equipment as listed below.
Equipment
Use
Ammeter
To check AC Voltage
and current (amperage)
Ohmeter
To measure resistance
(ohms) to ground
Refer to the wiring diagram(s) accompany
ing the motor and control box before re
connecting any electrical leads which have
been disconnected. Connections to the
wrong terminals may damage the motor
and/or control devices.
Voltage Imbalance
Use a voltmeter to read each phase of the incom
ing 3‐phase power. Each phase must balance with
the other two as closely as can be measured with a
commercial instrument. If the phases are out of
balance, contact your power company. If the
phases are balanced, check out the motor as de
scribed in the following steps:
a. Use a voltmeter, Amprobe, or equivalent in
strument to read the voltage of incoming
power lines 1 and 2, 2 and 3, and 1 and 3 at the
control box. Voltage must match as closely as
can be measured. If possible, measure the
voltage at the control box with:
1. The pump off.
2. The pump running in air.
3. The pump submerged and running under
full load.
The voltage measured under each condition must
be the same.
b. If voltage is balanced when the pump is off but
is imbalanced when the pump is running,
thoroughly check the power source, all inter
connecting cables, and the pump motor to
isolate the defect.
c. Use an Amprobe or equivalent instrument to
measure the current draw (amperage) of
each phase while the pump is running under
full load, and with no load. In each condition,
the amperage readings for all three phases
must match as closely as can be measured.
Normal amperage values are listed in Table 1,
Section B; these values apply only when the
voltage at the site is the normal voltage listed.
Motor and Power Cable Continuity
Set the megohmmeter at R x 1 scale and zero‐
balance it. Test as follows:
a. Shut off incoming power to the control box,
and disconnect the motor power cable leads.
Connect the megohmmeter test leads to any
two power cable leads, and note the megohm
meter reading. A high resistance reading indi
cates an open or broken circuit in the power
cable or motor windings, or a bad connection
between the motor and cable.
b. Repeat Step a. with each set of leads. The
three readings should be as close as can be
measured.
c. If readings indicate that continuity problems
exist in the motor or power cable, the motor
must be returned to the factory or to a Gor
man‐Rupp authorized repair facility.