1997 ignition update – Grain Systems PNEG-692 User Manual
Page 14

1998 Service School Top Dry
14
1997 IGNITION UPDATE
1997 Ignition Update Kit Installation Instructions
Packing List:
(1) HH-1093
2-pole Ignition Trans-
former
(4) S-2786
#8-32 x 3/8 Screw
(4) S-6555
18ga Butt Splice Con-
nector
(2) 00401174
Terminal Spade Tongue
(1) PNEG-627
Top Dry 97 Ignition
Update Kit Instruction
Tools Required:
One pair of wire cutters
One pair of wire strippers
One pair of crimpers
One drill with a Phillips screw bit
Installing the new two pole
ignition transformer
1)
Remove the two insulated ignition
wires from the single pole ignition
transformer.
2)
Cut the two wires that go from the
terminal strip to the ignition trans
former so that you can splice the two
wires on the new transformer with the
wires from the terminal strip.
3)
Remove the four screws that mount
the single pole ignition transformer to
the control box.
4)
Remove the single pole ignition
transformer. This transformer is still
good and can be used in the future on
non-Series 2000 Top Dry units, or for
temporary replacements on Series
2000 Top Dry units.
5)
Mount the new two pole transformer to
the control box using the four 3/8
screws.
6)
Connect the two insulated ignition
wires to the two pole transformer using
the two fork connectors.
7)
Splice the two wires from the two pole
ignition transformer with the two wires
that were cut in step #2 using two of the
butt splice connectors.
Bi-Passing the ballast resistor(s):
1)
Remove two of the wires that are oppo-
site one another long ways on the ballast
resistor ( in systems with two ballast
resistors remove the two wires from one
of the ballast resistors).
2)
Splice these two wires together using
one of the butt splice connectors.
3)
Remove the other two wires from the
ballast resistor ( in systems with two
ballast resistors remove the wires from
the other ballast resistor).
4)
Splice these two wires together using
the last butt splice connector.