beautypg.com

Assembling the center collar, Chapter 7: roof assembly – Grain Systems Tanks PNEG-4105 User Manual

Page 105

background image

Chapter 7: Roof Assembly

D

1/2 x 1-3/4 in. flange bolt (S-10252)

I

Assembled A-frame

E

1/2 in. flange nut (S-10253)

Weight of an Assembled Double A-frame

105 ft. Double A-frame

Approximate Weight

1390 lb (630 kg)

Assembling the Center Collar

The center collar assembles each A-frame roof rafter section together at the top.

Before You Begin
Determine the correct orientation of the center collar in relation to any stairs or conveyor systems. Each
half of the center collar (A) has drilled holes for the installation of the cap plate and side plates that will be
installed later. For this procedure, each half of the center collar needs to sit securely on stands or suitable
blocks, allowing plenty of room to access the bolts on the bottom side of the assembly.

1. Locate each half of the center collar (A), and install the center collar splice plate (D) to the inside por-

tion on the center collar.

2. Install flange bolts (E) and flange nuts (B) to the six center holes (H) located on the center collar

splice plate (D).

NOTE: The remaining open holes along the outside edge of the center collar splice plate (D) will be

used when installing the A-frame rafters to the center collar (A).

3. Install the second center collar splice plate (F) to the underside of the center collar (A), and install

flange bolts (C) and flange nuts (G).

Pneg-4105 105 Ft Diameter 40-Series Bin

105