Chapter 7: roof assembly – Grain Systems Tanks PNEG-4075G User Manual
Page 108
NOTE: The temperature cable bracket must be installed at specific locations, see
Cable Brackets and A-Frame Assemblies, page 76
1. Loosen and remove the flange bolts (E) and flange nuts (F) connecting the lower purlin clips (C and
D) and the rafter (A).
NOTE: If X-bracing was installed, loosen and remove the flange bolts and flange nuts attached.
2. Attach a temperature cable bracket (B) to the lower right purlin clip (D) and the roof rafter (A).
3. Install three flange bolts (E) and three flange nuts (F).
NOTE: If X-bracing is installed, make sure the flange bolts and the flange nuts are installed after it is
aligned with the purlin clips and the rafter.
4. Tighten all hardware to the recommended torque specifications. See
.
Figure 7-29 Installing a temperature cable bracket
A
Roof rafter
D
Lower left purlin clip (CTR-0631)
B
10 in. temperature cable bracket (CTR-0013)
E
1/2 x 1-3/4 in. flange bolt (S-10252)
C
Lower right purlin clip (CTR-0632)
F
1/2 in. flange nut (S-10253)
5. Install a quick link (C) to each cable bracket (B) to support the temperature cables.
IMPORTANT: Do not attach weights to the temperature cables; secure the bottom of cables to the
floor with light twine. No roof rafter shall support more than one cable.
108
Pneg-4075G 75 Ft Diameter 40-Series Bin