beautypg.com

Prepare boiler — pressure test, Gold cga gas-fired water boiler — boiler manual, Hydrostatic pressure test – Weil-McLain Gold CGa User Manual

Page 13: Drain and remove fittings

background image

Part Number 550-101-009/0107

13

GOLD CGa Gas-Fired Water Boiler — Boiler Manual

Prepare boiler — pressure test

Hydrostatic pressure test

Pressure test boiler

before

attaching water or gas piping

or electrical supply (except as noted below).

Prepare boiler for test

1. Remove the shipping nipple (from CGa supply

tapping) and remove the boiler relief valve.

Tempo-

rarily

plug the relief valve tapping with a ¾” NPT

pipe plug.

. Remove 1¼” nipple, reducing tee and drain valve

from accessory bag. Install in boiler return con-

nection as shown on page 3 or in

Figure 34

, item

3, page 4. Install circulator on either the return or

supply.

3. Remove 1¼” nipple, 1¼” tee, bushing and pres-

sure/temperature gauge from accessory bag. Pipe
to boiler supply connection as shown in

Figure 34

,

page 4. (Use pipe dope sparingly.)

4. Connect a hose to boiler drain valve, the other end

connected to a fresh water supply. Make sure hose
can also be used to drain boiler after test.

5. Connect a nipple and shutoff valve to system supply

connection on the 1¼” tee. This valve will be used
to bleed air during the fill. (Valve and nipple are
not included with boiler.)

. Connect a nipple and shutoff valve to system

return connection (at circulator flange if circula-
tor installed on return). This valve will be used to
bleed air during the fill. (Valve and nipple are not
included with boiler.)

Fill and pressure test

1. Open the shutoff valves you installed on supply and

return connections.

. Slowly open boiler drain valve and fresh water sup-

ply to fill boiler with water.

3. When water flows from shutoff valves, close boiler

drain valve.

Drain and remove fittings

1. Disconnect fill water hose from water source.
. Drain boiler at drain valve or out hose, whichever

provides best access to drain. Remove hose after
draining if used to drain boiler.

3. Remove nipples and valves unless they will remain

for use in the system piping.

4. Remove plug from relief valve tapping. See Section

3

to replace relief valve.

Do not use

petroleum-based

clean-

ing or sealing compounds in boiler

system. Severe damage to boiler

will occur, resulting in substantial

property damage.

Leaks must be repaired at once

.

Failure to do so can damage boiler,

resulting in substantial property

damage.

2b

4. Close shutoff valves.
5. Slowly reopen boiler drain valve until test pressure

of not more than 45 psi is reached on the pressure/

temperature gauge.

. Test at no more than

45 psi for no more than 10

minutes.

Do not leave boiler unattended

.

A cold water fill could expand and

cause excessive pressure, resulting

in severe personal injury, death or

substantial property damage.

. Make sure constant gauge pressure has been main-

tained throughout test. Check for leaks. Repair if

found.