SECTION O: ADB INITIAL START-UP
1.0
TOOLS NEEDED
•
One 8-0-8 , 16” scale manometer (or larger)
•
Three 4-0-4, 8” scale manometers (or larger)
•
“T” fitting
•
7/16” and 1/2" open end wrenches
•
Small and large flat-head screwdrivers
•
Volt meter
•
Amp probe
•
Elec. Dual reading thermometer with strap on sensors
•
3/16” Allen wrench
•
Remote switch with 12" minimum lead wires (“Monkey” switch)
•
Combustion analyzer
2.0
PREPARATION FOR START-UP
WARNING:
DO NOT TURN ON GAS AT THIS TIME
2.1
Check Power Supply
With volt meter at incoming power check voltage between:
Hot - Common
(
approx
120 VAC)
Hot - Ground
(
approx
120 VAC)
Common - Ground
(< 1 VAC)
If Common - Ground is > 1 VAC - STOP: Contact electrician to correct ground failure. Warning: Failure to do this
may burn out 120V-24V transformer, or may cause other safety control damage or failure.
2.2 Attach Manometers to Measure Pressures (See Figure: O-1)
•
Attach 16" scale manometer to the first main gas shut-off valve pressure tapping, Location (1)
•
Attach one 8" scale manometer to the outlet side of the second main gas shut-off valve pressure tapping, Location
(2).
•
Attach one 8" scale manometer to the outlet side of pilot gas valve pressure tapping, Location (3).
•
Attach one 8" manometer to "T" fitting, air pressure switch, and aluminum tubing, Location (4).
Turn Off Main Gas Valve;
Turn Off Pilot Gas Valve;
Reset Low Gas Pressure Cut-off Switch;
2.3 Bleed Air from Gas Line
CAUTION: Make sure there is no ignition source in the boiler room
•
With power off, slightly open union outside the cabinet to bleed air.
•
Close union when you smell gas.
•
Wait minimum 5 minutes to clear the gas out of the boiler room before continuing.
59