PORT-A-COOL® Hazardous Location Units
*
I. SETUP
A. Unpacking the PORT-A-COOL@ unit.
The PORT A-COOL HAZARDOUS LOCATION MODELS (PAC2K36EP and PAC2K48EP) are shipped strapped to
a	plastic	pallet	with	a	large	cover	box	strapped	over	the	PORT-A-COOL® unit.	It	is	a	simple	matter	to	cut	the	strap	
and	remove	the	box	by	lifting	it	over	the	PORT-A-COOL® unit.	This	will	expose	the	plastic	dust	cover.	Remove	the	
dust	cover.	At	this	time	two	(2)	people	can	remove	the	PORT-A-COOL® unit	from	the	pallet.	Due	to	the	additional	
weight	of	the	unit	caution	should	be	taken	in	removing	the	unit.
B. Removing the cooling media. (Disconnect Power)
Caution- Disconnect power before performing this operation!!
The PORT-A-COOL® unit should now be exposed to allow removal of the cooling media (pads). The front
flap	must	be	removed	to	allow	access	to	the	cooling	pads.	Start	with	the	center	pad,	which	should	be	tilted	out	from	
the	top	and	lifted	out	of	the	drain	trough.	The	two	pads	to	either	side	of	the	center	pad	may	then	be	removed	in	
the	same	manner.	Should	you	desire	to	remove	the	two	outside	pads,	they	must	first	be	pulled	sideways	toward	the	
center	of	the	PORT-A-COOL® unit	until	they	clear	the	side	retainer.	They	may	then	be	removed	as	the	other	pads.	
Removal	of	the	pads	allows	for	inspection	of	the	interior	of	the	unit.	Make	sure	all	connections	are	tight	and	both	
motor	and	pump	are	secure.
D. Connecting the water and electricity.
Water Connection (PORT-A-COOL® unit must be upright and on a level surface.)
After the PORT-A-COOL® unit has been thoroughly tested at the factory, the special female/female adapter
is	connected	to	the	brass	bulkhead	connector	on	the	left	side	of	the	PORT-A-COOL@ unit (when	looking	at	the	fan	
side).	Simply	attach	a	standard	garden	hose	to	the	brass	female/female	adapter.
Verify that the rubber hose washer is in place before attaching, and tighten the fitting to guarantee that a
secure	connection	is	made.	Once	the	hose	connection	is	made,	water	may	be	turned	on	to	the	PORT-A-COOL® unit.	
Water	should	now	be	entering	through	the	float	valve	to	fill	the	sump	tank.
To verify that your connections are well made, manually lift the red float in the float valve until it seats
against	the	top	of	the	valve	housing.	The	water	flow	should	stop	and	the	inlet	connections	may	now	be	visually	
checked	for	leaks,	paying	particular	attention	to	the	hose	connection	to	the	float	valve	and	the	connections	to	the	
bulkhead	fitting,	these	connection	may	loosen	during	shipment.