Patterson-Kelley MOD-04 User Manual
Page 13

Modu-Fire
®
Gas-Fired Boiler
Installation
10
Gas Piping
Note: Install a sediment trap (drip leg) and a union 
connection ahead of the primary manual shutoff valve 
on the boiler. Gas piping should be installed in accor-
dance with National Fuel Gas Code, ANSI Z223.1, 
latest edition, and any other local codes which may 
apply; in Canada see CAN/CGA-B 149. 
 
Note: See chart below for required pipe size, based on 
overall length of pipe from meter plus equivalent 
length of all fittings. Approximate sizing may be based 
on 1 cubic foot of natural gas per 1,000 Btu per hour 
input, i.e., 900,000 Btu per hour requires about 900 
cubic feet per hour. (See Typical Boiler Operating 
Conditions, Section 4.3, for more information.) 
 
WARNING!
All threaded connections must be made using a pipe 
compound that is resistant to the action of liquefied 
petroleum gases. Do not use Teflon tape on gas line 
threads. 
 
Pipe Capacity for Natural Gas 
 
Equivalent Pipe Length
Maximum Capacity in Cubic Feet of Natural Gas per Hour
Pressure Drop of 0.5 inch Water Column/Equivalent Length of
Pipe (in feet)
Nominal
Iron
Pipe
Size
(Inches)
Internal
Diameter
(Inches)
90º Ell
(Feet)
Tee
(Feet)
20
40
60
80
100
150
200
1-1/4
1.380
3.45 6.9
950
1-1/2
1.610
4.02 8.04
1,460
990
810
2
2.067
5.17
10.3
2,750 1,900 1,520 1,300 1,150 950 800
2-1/2 2.469
6.16
12.3
4,350 3,000 2,400 2,050 1,850 1,500 1,280
3
3.068
7.67
15.3
7,700 5,300 4,300 3,700 3,250 2,650 2,280
4
4.026
10.1
20.2 15,800
10,900 8,800 7,500 6,700 5,500 4,600
 
 
By Installer
Remote Gas
Shutoff (not
supplied)
Drip Leg
Union
Shutoff (on
boiler)
Gas Meter (not 
supplied) 
