1

Determine boiler location

(continued)

12"

(305 MM)

LEFT

13" (330 MM)

TOP

1" (25 MM) MINIMUM CLEARANCE
AROUND HOT WATER
PIPES AND VENT PIPE

14" (356 MM)

REAR

18" (457 MM)

FRONT

0"

RIGHT

OPEN

FRONT

ALCOVE INSTALLATION

Figure 1-2 Alcove Installation - Minimum Required Clearances

6" (152 MM)

13" (330 MM)

TOP

CLOSET INSTALLATION

1" (25 MM) MINIMUM CLEARANCE
AROUND HOT WATER
PIPES AND VENT PIPE

VENTILATING*
AIR OPENING

CLOSED DOOR

VENTILATING*
AIR OPENING

0"

RIGHT

6" (152 MM)

F RONT

14" (356 MM)

REAR

12" (305 MM)

LEFT

*AREA OF EACH OPENING:
1 SQ. INCH PER 1000 BTU PER HOUR INPUT
WITH A MINIMUM OF 100 SQ. INCHES

Figure 1-1 Closet Installation - Minimum Required Clearances

ƽ WARNING

For closet installations, CPVC or
stainless steel material MUST BE
used in a closet structure due to
elevated temperatures. Failure to
follow this warning could result in
fire, personal injury, or death.

RECOMMENDED SERVICE CLEARANCES:

Front

- 30" (762 mm)

Top

- 24" (610 mm)

Left Side - 24" (610 mm)
Rear -

24" (610 mm)

RECOMMENDED SERVICE CLEARANCES:

Front

- 30" (762 mm)

Top

- 24" (610 mm)

Left Side - 24" (610 mm)
Rear -

24" (610 mm)

ƽ WARNING

For alcove installations, CPVC or
stainless steel material MUST BE
used in an alcove structure due to
elevated temperatures. Failure to
follow this warning could result in
fire, personal injury, or death.