35

RELIEF VALVE

TEE WITH 3/4” FITTING ON TOP

CLOSE NIPPLE (FIELD PROVIDED)

CLOSE NIPPLE

TEE WITH FITTING ON TOP

(FIELD PROVIDED)

TEMPERATURE AND

PRESSURE

GAUGE

PADDLE

FLOW SWITCH

CLOSE NIPPLE

TEE WITH 1” FITTING ON TOP

CLOSE NIPPLE

NOTICE

Be sure to install the flow switch so that
the arrow on the flow switch is pointing
in the direction of the flow (see FIG.
6-3).

Figure 6-2 Flow Switch, Relief Valve and Temperature and
Pressure Gauge Installation_Models 600 - 800

Flow switch,

relief

valve and

temperature and pressure gauge
installation

Basic steps are listed below to guide you through the
installation of the flow switch, relief valve, and temperature
and pressure gauge provided with the unit.

1.

For Models 399 - 500 install the close nipple on the
outlet connection of the heat exchanger. Install the tee
with the 3/4 inch fitting positioned vertically and on
the top as shown in FIG. 6-1. For Models 600 - 800
install the tee directly to the outlet connection of the
heat exchanger with the 3/4 inch fitting positioned
vertically and on the top (see FIG. 6-2).

2.

For Models 700 - 800 install the 3/4 inch close nipple
in the tee. Install the relief valve on the 3/4 inch close
nipple (FIG. 6-2). For Models 399 - 600 install the
relief valve directly into the 3/4 inch fitting on the tee
(FIG. 6-1).

3.

Install the close nipple on the downstream side of
the relief valve tee (FIG. 6-1).

4.

Install the tee with the 1 inch fitting positioned
vertically and on the top (FIG. 6-1).

5.

Attach paddle #3 to the flow switch per the
manufacturer’s instructions.

6.

Install the assembled flow switch into the 1 inch fitting
of the tee installed in Step 4 (see FIG. 6-1).

7.

Install a field provided close nipple on the downstream
side of the flow switch (see FIG.’s 6-1 and 6-2).

8.

Install a field provided tee with the gauge fitting
positioned vertically and on the top (FIG.’s 6-1 and
6-2)

9.

Install the temperature and pressure gauge provided
with the unit into the top fitting of the tee (a bushing
may be necessary) installed in Step 8 (FIG.’s 6-1 and
6-2).

RELIEF VALVE

TEE WITH 3/4” FITTING ON TOP

CLOSE NIPPLE (FIELD PROVIDED)

CLOSE NIPPLE

TEE WITH FITTING ON TOP

(FIELD PROVIDED)

TEMPERATURE AND

PRESSURE

GAUGE

PADDLE

FLOW SWITCH

CLOSE NIPPLE

TEE WITH 1” FITTING ON TOP

Figure 6-1 Flow Switch, Relief Valve and Temperature and
Pressure Gauge Installation_Models 399 - 500