beautypg.com

9 hand-over to the operator, Hand-over to the operator – SMC Networks Sunny Mini Central SMC 5000A User Manual

Page 57

background image

SMA

Technologie AG

Hand-over to the Operator

Installation Guide

SMC50A_60A-IEN073320

Page 57

9 Hand-over to the Operator

After installing the Sunny Mini Central successfully, hand the system over to the
operator. To do so, please use the following check list.

No.

Checkpoint

Control

What the operator should know:

1

operating principles of the PV system

2

switching the PV system on and off

3

meaning of the LEDs and display messages

4

maintenance and cleaning (handle covers, LEDs, display,...)

5

handling of additional communication components

6

contact partner in case of a failure

7

keep the documents to hand close to the Sunny Mini Central

The following documents are handed over to the operator:

1

operating manual of the Sunny Mini Central

2

installation guide of the Sunny Mini Central

3

declaration of conformity of the Sunny Mini Central

4

if necessary, all manuals for additional components (interfaces,
data logger, etc.)

5

data sheet for the solar modules used

6

diagram of the layout of the solar modules and their wiring

7

current circuit diagram of the unit

8

the complete registration and commissioning documents of the
local energy supply company

This manual is related to the following products: