STEP 3: CHECK FOR 24 VAC AT TRANSFORMER CN4 PLUG ON CONTROL BOARD.
Condition:

• CN4 is plugged into control board.
• On/Off switch is on.

Insert meter probes into back of CN4 plug on pins 3 and 4 (blue and yellow wires) with CN4
plugged in and power on.

STEP 3

24 VAC FROM TRANSFORMER

IF…

THEN

24 VAC is not present

replace transformer if Steps 1 and 2 were performed and results were successful.

24 VAC is present

continue to Step 4.