Securing tub – Invacare 3600XL User Manual
Page 16
SECTION 2—PARTS AND INSTALLATION
16
Securing Tub
NOTE: For this procedure, refer to FIGURE 2.2.
1. Set the tub in place.
2. Ensure plumbing and electrical hook‐ups have been installed. Refer to Electrical and
Plumbing Hook‐up Locations on the Tub on page 17, Electrical Installation on page 17
and Plumbing Installation on page 20 to ensure the proper hook‐ups have been
installed before securing the tub.
3. Mark location of anchor holes, using pre‐drilled holes in leg mounting pads as a
template.
4. Move tub away from mounting area.
ƽ WARNING
Protective eye wear MUST be worn when drilling to avoid possible eye injury.
5. Drill anchor holes in floor. Use jack‐drill and carbide bit in concrete or a wood bit for
wood floors.
6. Reposition the tub in mounting area, aligning the holes in the leg mounting pads with
the holes drilled in STEP 4.
ƽ WARNING
DO NOT adjust height of legs more than 1 inch (25.4 mm) for Model 3650 or 2
inches (50.8 mm) for Models 3600 and 3600XL; leg will disassemble from leg
mounting pad and serious injury may occur.
7. Level the tub by adjusting the telescopic legs either up or down, using a wrench, to
arrive at the desired height.
8. Check to make sure tub is level by placing a level on the front and sides of the tub.
9. Repeat STEPS 6 and 7 until tub is level.
10. Secure legs to floor using fasteners appropriate to the floor material and in keeping
with any local codes.
FIGURE 2.2 Securing Tub
LEVELING END TO END
LEVELING SIDE TO SIDE
Level
Level
Lag
Bolt
Leg
Leg
Mounting
Pad
Anchors
Maximum Adjustment
• 1-inch (25.4 mm) for
Model 3650)
• 2-inch (50.8 mm) for
Models 3600 and 3600XL
Securing Legs to Floor
Lag Bolt