Installation, Quick installation outline, Site requirements – Metrologic Instruments StratosS MS2220 User Manual
Page 17: Vertical clearance, Ventilation and spacing, Service access, Nstallation
11
I
NSTALLATION
Q
UICK
I
NSTALLATION
O
UTLINE
The following is a quick preview of the steps required for 1
st
time installations. Each item is discussed in detail later in this
section.
• Determine clearance, ventilation and service access requirements.
• Determine checkout counter layout taking into account package flow, cable routing and power requirements.
• Choose the mounting option which provides the best cable/power access and unit stability.
• Unpack the unit.
• Make the appropriate countertop cutouts and install all support brackets.
• Place the unit in the counter.
• Install the platter.
• Follow the steps under the correct interface to connect the cables and power supply.
• Configure the unit for the correct interface.
• Calibrate the Diva scale.
S
ITE
R
EQUIREMENTS
Before installing your StratosS scanner/Diva scale, please consider the following items.
Vertical Clearance
A minimum clearance height of 5.25" from the checkout counter surface is needed for the vertical 'hood' on all of the scanner
models.
Ventilation and Spacing
All StratosS models have a die-cast housing to dissipate heat allowing the unit to operate without a ventilation fan. Metrologic
recommends that the temperature surrounding the unit does not exceed 40°C (104°F). There should be adequate convection
and minimal heat producing equipment in close proximity of the unit.
A cooling fan with a filter is recommended if there will be a conveyor motor or other heat producing equipment close to the unit
that will create a high temperature environment.
Adequate spacing between the unit and the checkout counter opening is required for proper operation of the scale. When the
scanner/Diva scale model is mounted properly, the scale platter should be able to move up and down freely without hitting the
edges of the checkout counter cutout. Refer to Installing the Unit in the Counter beginning on page 14 of this guide for
detailed cutout dimensions and mounting instructions.
Service Access
When routing and installing the cable(s) and power supply, make sure you leave access that these components may be
swapped easily without the need to remove the unit from the checkout counter.
When changing the StratosSWAP™ optics engine modules, Metrologic recommends removing the unit completely from the
checkout counter.
When calibrating or zeroing the scale, do not remove the unit from the checkout counter. Refer to the Scale Operation Section
beginning on page 39 of this guide for detailed instructions on zeroing and calibration.