Preparing to Install the Lift

Final Site Inspection

Verify the surface the lift will mount to is smooth and level. This surface must be made from 3,500 psi
reinforced concrete with a minimum thickness of 4”.
Verify that there is enough space for the lifts foot print. Be sure to include space neccesary for platform.

Caution: Verify that the running clearance around the lift complies with
any codes for your area.

• The horizontal gap between the edge of the platform and the upper landing must no less than 3/8”

and no greater than 3/4”.

• The horizontal gap between the guard panel and any wall or barrier must be no less than 2” and

no greater than 3”.

• Verify that sufficient head room exists above the lift. The lift will require 6’ 8” of clearance above

the platform floor when the lift is at the upper landing.

Warning: The area between the floor where the lift is mounted and the top
landing must be covered by a smooth vertical fascia. This is to to eliminate any pinch
points between the platform and landing.


Connecting to Electricity

The lift will require a 115 VAC 20 amp grounded electrical circuit.
Depending on local codes, this connection may need to be routed in electrical conduit and hard-wired.

Warning: Do not ride on the lift until it has been anchored in place

.

Controller Harness Connections






5

High Voltage 

Circuit Breaker 

(AC unit only) 

Low Voltage 

Circuit Breaker 

Platform 

Traveling Cable 

Phone Jack 

Connection 

Safety Pan 

Jumper

Upper Landing 

Interlock

Lower Landing 

Interlock

Upper & Lower 

Call‐Sends

Upper & Lower 

Limit Switches 

Bypass Switches 