Site Planning Data, Liebert FS Flywheel Energy Storage System: 190 kW, 10 Seconds

Nominal Energy

Storage

Recharge

Discharge

Rotational Speed

Mechanical Data

Max. Current

ADC

Nom. Voltage

VDC

Nom. Power

kW

Duration

seconds

Nom. Voltage

VDC

Min.

rpm

Max.

rpm

Dimensions

W x D x H, in. (mm)

Weight

lb. (kg)

Losses

(W)

1900 kW-seconds

50

520

190

10

510

25,000

55,500

25 x 32.5 x 71

(635 x 826 x 1803)

1300 (590)

< 300

See Notes for Table (below):

1, 11

2, 11

4

4

3, 11

Notes for Table

1. Recharge current shown is the maximum the Liebert FS can accept. This

value is dependent on the UPS, typically limited to 15% of the UPS’s nominal

full load DC current.

2. Recharge voltage is adjustable, 480 to 500VDC. 190kW requires >520VDC.
3. Discharge voltage is adjustable, 480 to 500VDC. 190kW requires >510VDC.
4. Discharge rates below 190kW increase the discharge duration time (see

Figure 1). In addition, the FS has the capability to discharge at rates above

190kW for shorter discharge durations. Please consult factory for details.

5. Power cable from UPS DC bus to Liebert FS should be sized for total

maximum 2.0 volt line drop (power cable plus return cable drop as measured

at the module) at maximum discharge current.

6. Grounding conductors to be sized per NEC 250-95.
7. All wiring to be in accordance with National and Local Electrical Codes.
8. Minimum clearance is 3 ft. (0.9m) in front and 1 ft. (0.3m) above the

Liebert FS.

9. Exterior cable entry available through removable top access plates: remove,

punch to suit conduit size and replace.

10. Control wiring and power wiring must be run in separate conduit.
11. When used with the Liebert Series 300, nominal recharge voltage is

395VDC, nominal discharge voltage is 385VDC, with adjustable range of 360

to 405VDC for both. Due to lower VDC, power output below 30 seconds must

be derated. Contact factory for details.

12. AC auxiliary power input required: 110/230VAC, 1 ph, 400VA.

Additional Notes

• If site configuration includes a backup emergency generator, it is recom-

mended that the engine generator is set to be properly sized and equipped for a

UPS application. Generator options would typically include an isosynchronous

governor (generator frequency regulation) and a UPS-compatible regulator

(generator voltage regulation). Consult the generator manufacturer for

required generator options and sizing.

Figure 1

DC bus power duration

1900 kW-sec delivered

GT model, 510 VDC, with filter

10 seconds at 190kW (max. power)

@ 510 VDC min

© 2007 Liebert Corporation
All rights reserved throughout the world.
Specifications subject to change without notice.

SL

-29305_REV04_04-07

® Liebert and the Liebert logo are registered
trademarks of Liebert Corporation. All names referred
to are trademarks or registered trademarks of their
respective owners.

Liebert Corporation

1050 Dearborn Drive
P.O. Box 29186
Columbus, OH 43229

Telephone: 1-800-877-9222
Facsimile: 1-614-841-6022
www.liebert.com