7  Requirements for Commissioning

Installation Manual

SMB-IA-en-10

25

7 Requirements for Commissioning

During commissioning of the Sunny Main Box or Sunny Main Box Cabinet, the commissioning report
must be filled in. The commissioning report is enclosed with the central inverter.
Requirements:

☐ The DC input cables are connected to the inverter and are activated. There is no reverse voltage

from the inverter.

☐ All connections are executed according to this manual (see Section 6 "Electrical

Connection", page 20).

☐ It has been verified that all fuses are firmly in place.
☐ The ground around the Sunny Main Box or Sunny Main Box Cabinet is paved and provides

suitable access.