Receiving and Unpacking Equipment
Check packing slip to ensure ALL material has been delivered.
All material shortages are to be reported to Nortec within 48 hours from receipt of goods. Nortec
assumes no responsibility for any material shortages beyond this point.
Inspect shipping boxes for damage and note on shipping waybill accordingly.
After unpacking, inspect equipment for damage and if damage is found, notify the shipper
promptly.
All NORTEC products are shipped on an F.O.B. factory basis. Any and all damage, breakage, or loss
claims are to be made directly to the shipping company.
Each distributor is provided with: installation manual, one hose cuff, and two hose clamps.
Pre-Installation Check
Ensure the total capacity of the humidifier is not higher than the allowable maximum steam capacity of
the distributors used.
ASD 10: 22 lbs/hr (8 kg/hr)
ASD: 25 lbs/hr (9 kg/hr)
BSD: 35 lbs/hr (13 kg/hr)
CSD: 115 lbs/hr (45 kg/hr)
Steam Line Installation
NORTEC steam hose should only be used on short steam runs below 10 feet.
Ensure that no condensate produced in the steam line will remain trapped. Steam naturally flows
upward and condensate naturally flows downward.
See material recommended for use in the chart below. To eliminate the metal corrosion, NORTEC
does not recommend the use of steel piping.
Consult the following pages for step by step distributor installation starting with Figure 1.
Consult the charts below for steam and condensate sizing guidelines when using steam