Venting installation instructions, Continued – Desa (V)VC42NE User Manual
Page 11
11
11
www.desatech.com
116237-01A
Vertical (V)
Required
Vertical (V) Vertical Pipe Horizontal (H)
*43
1
/
2
" min.
None
30" max.
54
1
/
2
" min.
1 ft.
48" max.
66
1
/
2
" min.
2 ft.
60" max.
78
1
/
2
" min.
3 ft.
84" max.
90
1
/
2
" min.
4 ft.
20' max.
* Ground Floor Corner Venting
Figure 15 - Horizontal Termination Configuration for Corner Installation Using One 90° Elbow
Square
Termination
Wall
Firestop
Not to Exceed
(H) Limits
As Required for (V)
See Chart for Pipe
Section Required
45°
Elbow
90° Elbow
90° Elbow
Square
Termination
Wall
Firestop
45° Elbow
Not to Exceed
(H) Limits
12" Minimum
CORNER INSTALLATION
Recommended Applications:
• Corner ground floor installation
• Ground floor installation where pipe vents horizontally through wall
(over 12" horizontal pipe)
• Basement installation where one foot clearance from ground to
termination is possible
SNORKEL TERMINATION INSTALLATION
Recommended Applications:
• Installations requiring a vertical rise on building exterior
• Any installation using snorkel termination to achieve one foot above ground
Snorkel terminations are available for installations requiring a vertical rise on the exterior of the building. If install-
ing snorkel termination below grade, you must provide proper drainage to prevent water from entering snorkel
termination (see Figure 16). Do not back fill around snorkel termination.
VENTING INSTALLATION
INSTRUCTIONS
Continued
VENTING INSTALLATION INSTRUCTIONS
Installation Planning (Cont.)
Snorkel
Termination
12"
Minimum
Snorkel
Termination
Wall
Firestop
90° Elbow
45°
Elbow
Figure 16 - Snorkel Termination Configurations for Below Ground Installation
12"
Minimum
12"
Minimum
Snorkel
Termination
Adequate
Drainage