READY FOR WELDING
When you have completed all of the previous steps to prepare for welding, including
connecting the stud gun and ground cables to the unit, attaching the ground cable(s)
to the work area, setting up and adjusting the stud gun for the selected stud diame‐
ter and material, you can now power on the welder.
The controller ON/OFF switch is located on the rear of the unit in the upper right
hand corner. Below this switch is the 15amp fuse holder for the system.