Installation procedures – Pinnacle Systems CA User Manual
Page 16

- A - 8 -
Installation Procedures
Model CA Cascading Safety Light Curtain
Operations
NOTE: Examine the Model CA on a daily basis to make 
sure that the curtain pylons have not been moved and 
that any mechanical guarding has not been moved or 
removed.
WARNING: If it is possible for someone to go through 
the light curtain and remain between the curtain and 
the hazard without blocking the curtain, you must wire 
your “Safety Relay Module” for manual reset, or install a 
safety mat or horizontal light curtain to guard this area.
1) APPLY POWER: The curtain (both pylons) will go 
through a power up test. First, both Yellow and Green 
lights blink 1 time. This indicates the Master and Slave 
processors are functioning properly. Second, both Yel-
low and Green lights blink 2 times. This indicates Master 
and Slave are now in sync with each other. 
2) SYNCHRONIZATION: The curtain will now deter-
mine if the CAN data network is installed. Third, The 
Green lights will blink: 2 times for infrared synchroniza-
tion between pylons, 3 times for CAN data network syn-
chronization between pylons. If infrared synchronization 
is used, the Yellow status light on the Emitter pylon will 
be on (dim) all the time, with the Red status light blink-
ing periodically, the Receiver pylon will indicate output 
status. If the CAN data network is used, the Emitter 
status lights will indicate the current pylon output status 
(just like the Receiver side).
3) STATUS INDICATORS: Solid Green=Curtain clear 
(no blockage, or faults) and outputs active (+24vdc out). 
Solid Red=Curtain blocked and outputs off (open). Solid 
Yellow= Curtain in either AutoBlank or FloatingBlank 
modes. Blinking lights indicate a fault condition and 
the outputs will be off (open) (see Fault Codes section)
IMPORTANT: OUTPUTS 1 & 2 MUST BE USED 
WITH EITHER “CONTROL RELIABLE” PLC INPUT 
CIRCUITS OR A SAFETY RELAY MODULE. 
WARNING: NEVER USE OUTPUTS 1 & 2 TO 
CONTROL RELAY(S) OR VALVE(S).