J.
Install the carburetor in the enclosure until it sits
flat on the flange.
K. Install two of the brass plugs in each side of the
carburetor enclosure. Make sure the copper crush
washers are installed between the brass plugs
and the enclosure. (See
Fig. 8.)
L.
Install the idle bracket on the outside of the
enclosure using two 1/2” screws. (See
Fig. 9.)
M. With the one armed throttle arm on the inside of
the enclosure, insert the splined shaft through
the throttle bushing on the side of the carburetor
enclosure.
N. Install the large brass spacer over the splined
shaft until it rests flat against the outside of the
enclosure. (See
Fig. 9.)
O. Line up the two armed throttle arm with the inner
throttle arm and slide onto the splined shaft.
P.
Tighten the clamp screws on both of the throttle
arms. Rotate the throttle linkage to verify free
movement. If drag is felt, adjust the distance
between the two throttle arms.
Q. Install the remaining rod end on the outer hole on
the inside of the inside throttle arm and tighten
screw.
R. Install the carburetor over the carburetor studs
until it sits flat on the gasket.
S.
Install the four 5/16” nuts and washers on the
studs and tighten.
T.
With a jam nut installed on each rod end, install
the 5/16” coupler shaft between the two rod ends.
Adjust the coupler until the angle of the carbure-
tor enclosure throttle arm matches that of the
carburetor throttle arm.
U. Install the supplied 10-32 jam nut on the 1” 10-32
screw and insert into the idle bracket. (See
Fig. 9.)
V.
Install the fuel lines on the carburetor. See Fig. 10
if optional Vortech fuel lines are used, and pro-
ceed with the following steps:
1.
Install the -8 bulkhead nut and O-ring on the
bulkhead fitting.
2.
Thread the bulkhead fitting into the front
hole in the carburetor enclosure.
3.
Install the fuel lines into the carburetor bowls
loosely.
4.
Connect the free end of each fuel line to the
-8/-6/-6 TEE.
5.
Install the -8 straight hosebarb fitting on the
inside of the bulkhead fitting. Install the -8
120
°
fitting on top of the TEE.
6.
Measure and cut the supplied pushlock
hose so that it will fit well between the two
installed barb fitttings.
NOTE: The 10-24 screw should not
protrude past the nut. Use
washers as necessary to ad-
just the thread depth.
2
CARBURETOR ENCLOSURE INSTALLATION, cont’d.
Fig. 9
Fig. 8
Fig. 7
Brass Plugs w/Copper Washers