4. DETAILED OPERATING INSTRUCTIONS
2. IF TEST FAILED
The Fail lamp illuminates if the discharge has been 
discontinued because the cutoff voltage has been 
reached before the completion of the set discharge 
time. The red LED goes out, but the time is frozen at 
the elapsed time at which the test failed. The battery is 
in need of reconditioning or must be rejected for 
aircraft service. Refer to the battery manufacturer's 
maintenance manual on how to proceed. 
4.7.1 LEAD-ACID BATTERY 
If the lead-acid battery has been accepted by the Beta D-50 discharge test it has 
successfully completed the capacity test. 
 
4.7.2 NICKEL-CADMIUM BATTERY 
Check each cell with a digital voltmeter near the end of the test. 
A. If no cells have dropped below 1.0 volts at the end of the specified time the battery 
has successfully completed the capacity test. 
B. If any cells have dropped below 1.0 volt before or at the end of the capacity test the 
battery must be reconditioned (deep cycled). Please refer to the battery manufacturer's 
maintenance manual on how to proceed. 
K.
SWITCH AC POWER OFF.
Switch the AC on-off/reset switch off before 
removing the battery 
 
 
NOTE: If in emergency it is required to stop the test, 
switch the unit to off/reset. When the test is restarted the 
timer is reset to zero. It may be necessary to recharge the 
battery before resuming the test. 
 
 
 
 
BETA D-50 TESTER / ANALYZER - OPERATING MANUAL V2.2