6 Commissioning
Diagram 6.4
BURNER
SUPPLY
TUBE
PILOT SUPPLY TUBE
BLUE
GREEN/YELLOW
BROWN
THERMOCOUPLE
NUT
5312
COVER
COVER
SECURING
SCREW
GAS SERVICE
COCK
MULTI-FUNCTIONAL
CONTROL
Relight the main burner and allow the system to warm up.
There should be no undue noise in the system and no pumping
over of water or entry of air at the open vent.
Allow the system to reach maximum temperature and check for
water soundness.
The burner should then be turned off and the system drained,
as rapidly as possible, to complete the flushing process. Refill
the system, heat up, vent and check again for water soundness.
If the side panels are to be fitted, remove the outer case. (Fit by
fastening to the outer case using the securing screws, see
diagram 6.5.)
Refit outer case and controls cover.
7 User Information
Hand the Instructions for Use to the user for their retention.
Instruct and demonstrate the efficient and safe operation of the
boiler, the heating system and if installed the domestic hot water
system.
Advise that to ensure the continued efficient and safe operation
of the boiler it is recommended that it is checked and serviced
as necessary at regular intervals. The frequency of servicing
will depend upon the particular installation conditions and
usage, but in general once a year should be enough.
Draw attention, if applicable, to the current issue of the Gas
Safety (Installation and Use) Regulations, Section 35, which
imposes a duty of care on all persons who let out any property
containing a gas appliance.
It is the Law that any servicing must be carried out by a
competent person.
Advise that the boiler is fitted with a safety device and refer to
the Instructions for Use.
Advise the user of the precautions necessary to prevent damage
to the system and building in the event of the heating system
being out of use during frost or freezing conditions.
Reminder, leave these instructions and the ‘Benchmark’ logbook
with the user.
8 Servicing and Replacement of Parts
To ensure the continued efficient and safe operation of the
boiler it is recommended that it is checked and serviced as
necessary at regular intervals. The frequency of servicing will
depend upon the particular installation conditions and usage,
but in general once a year should be enough.
It is the Law that any servicing must be carried out by a
competent person.
BEFORE SERVICING OR REPLACING PARTS TURN OFF
THE GAS SUPPLY AND ISOLATE THE ELECTRICAL SUPPLY
TO THE BOILER.
AFTER COMPLETING A SERVICE OR REPLACEMENT OF
GAS CARRYING COMPONENTS ALWAYS TEST FOR GAS
SOUNDNESS AND CARRY OUT FUNCTIONAL CHECKS ON
CONTROLS.
Unless stated otherwise replacement of parts is in the reverse
order to removal.
Check that the boiler thermostat and all external controls are
operating as required.
Do not attempt to adjust the thermostat calibration screw.