Dunkirk Helix VLT Vertical Laser Tube, Wall Hung Modulating Condensing Boiler User Manual

Page 5

background image

5

SECTION A

Stainless Condensing boiler working with HIGH

Temperature Heating Device

A1. Pipe the system

1-1. Pipe the heating system and install all required

components following installation instructions of

Additional Heating Device, i.e. a wood boiler.

1-2. Connect the Additional Heating Device and

Stainless Condensing boiler together as shown in

Figure A1. If the Additional Heating Device can be

pressurized.

1-3. Install Stainless Condensing boiler System Sensor

on the supply side of the piping (supply side of

Additional Heating Device) as shown in Figure A1.

If the Additional Heating Device CAN NOT be

pressurized (i.e. and open system) connect the

Stainless Condensing Boiler and Additional Heating

Device as shown in Figure A2.

1-4. All near boiler piping requirements of the

Additional Heating Device have to be satisfied.

Refer to installation and operation manuals of the

Additional Heating Device.

1-5. Manufacture recommends Additional Heating

Device bypass valve. Close the

bypass valve when

Additional Heating Device is used. When Additional

Heating Device will not supply heat for extended

period of time, open the bypass valve. This is

important when Additional Heating Device is an

outdoor wood boiler. Water from the system will

not be cooled from circulating through the unused

system.

1-6. Install expansion tank, air vent, and filling pipe at

upstream (inlet) side of system pump.

A2. Connect Electrical Wires

2-1. Follow instructions in Additional Heating Device

manuals when wiring

(1) all high voltage wires

and

(2) Low voltage wires other than Call For Heat

wire.

2-2. Follow instructions in Stainless Condensing boiler

Installation, Operation and Maintenance Manual

when connecting

(1) all high voltage wires

and

(2) Low voltage wires other than Call For Heat

wire.

2-3. Connect system pump to Additional Heating

Device, if applicable.

2-4. All zone pumps and zone valves, if controlled

by heating device, should be connected to and

controlled by the Additional Heating Device, if

applicable.

2-5. Remove or deactivate Low Limit control on

Additional Heating Device, if available.

A3. Connect CH Call For Heat Wires

3-1. Install one of the supplied call for heat controls,

AR822, onto wall.

3-2. Remove jumper in AR822 between Terminal-L1

and Terminal-3.

3-3. Connect Additional Heating Device and Stainless

Condensing boiler. See Figure A3.
• Connect two wires, from room thermostat or

from zone control board, to input T-Terminals

(Terminal-R and Terminal-W) in AR822.

• Connect Terminal-5 and Terminal-6 in AR822 to

Stainless Condensing boiler CH T-T terminals.

• Connect Terminal-3 and Terminal-4 in AR822 to

CH T-T input of Additional Heating Device.

• Connect line voltage wires to Terminal-L2 and

Terminal-L1 in AR822.

A4. Connect DHW Call For Heat wires, if applicable

4-1. Install supplied call for heat control, AR822, onto

wall.

4-2. Remove jumper in AR822 between Terminal-L1

and Terminal-3.

4-3. Connect Additional Heating Device and Stainless

Condensing boiler following Figure A4.
• Connect two wires, from hot water tank

thermostat or from zone control board, to input

T-Terminals (Terminal-R and Terminal-W) in

AR822.

• Connect Terminal-5 and Terminal-6 in AR822 to

Stainless Condensing boiler CH T-T terminals.

• Connect Terminal-3 and Terminal-4 in AR822 to

CH T-T input of Primary Heating Device.

• Connect line voltage wires to Terminal-L2 and

Terminal-L1 in AR822.

A5. Setting the Additional Heating Device

5-1. Set CH supply temperature setting of Additional

Heating Device according to heating system

requirement, i.e. 170°F.

5-2. Set DHW supply temperature setting of Additional

Heating Device according to hot water tank

requirement, i.e. 180°F.

SECTION A - STAINLESS CONDENSING BOILER OPERATING WITH HIGH TEMPERATURE HEATING DEVICE