Wall Mounting Instructions for Screens with 24” Marker Tray (continued)
5. Repeat Steps 3-4 to install the (4) remaining L-brackets for the side
panels.
NOTE:
At this point, all six L-brackets will be mounted on the wall;
two L-brackets for each panel. Do not proceed if all six-L brackets
are not level with each other on the wall.
Steps 6-7 require at least four people. Place one person on the
far left end of the screen, one person at the left panel seam,
one person at the right panel seam and one person on the far
right end of the screen. More people can be utilized as
needed. When lifting the screen off of the clean work area to
the wall and then onto the wall, it is crucial that the screen
remain coplanar and does not bend at the seams.
CAUTION: Any bend between the three panels at the seams
may damage the screen or result in a permanent gap
between the seams.
6. Using all four people, carefully lift the fully assembled three panel
screen to an upright position and place underneath the mounted
wall and L-brackets. The screen will be parallel to the wall at the
end of this step.
7. Using all four people, carefully and in a smooth motion lift the
screen to hang it on the four installed wall brackets. There is a lip
on the back of the frame that wedges itself into the four wall
brackets once full installed. Ensure that the screen clears the six
L-brackets and that the screen weight is on the four wall brackets,
not the six L-brackets.
8. Center the aluminum tray to the bottom of the center panel
frame and attach with (3) of the provided #8 x 1/2” screws. Insert
screws through the tray into the groove (Figure 4).
9. Tap the bottom of the six L-brackets with the rubber mallet until
they make contact with the frame. Secure the six L-brackets to the
frame with the remaining (12) #8 x 1/2” screws (Figure 4).
Figure 4
#8 X 1/2" Screws