10

Unit Preparation

7. Ensure constant gauge pressure has been

maintained throughout the 10 minute test.
Check for leaks at all fitting joints. Repair
if found.

Leaks must be repaired immediately
when detected. Failure to repair leaks
can damage the unit, resulting in sub-
stantial property damage.

8. Check continuity using a voltmeter across

the terminals of the LWCO device. The
contacts on the LWCO should be closed.
See item 6 in Fig. 24 page 47 for location
of the LWCO.

Completion of Hydrostatic Test and Draining

1. Disconnect the fill hose from the fresh

water source and direct the hose to a suit-
able place of drainage.

2. Open the primary drain valve and complete-

ly drain the unit. To aid in draining, open the
shut-off valve on the primary supply.

3. Remove the hose from the primary drain

valve when draining is complete.

4. Remove the plugs, nipple, shut-off valve

and any other piping unless they will
remain for use in the system piping.

WARNING

This manual is related to the following products: