Operation, Before starting – MTD 24638S User Manual
Page 7
Attention! The text in this document has been recognized automatically. To view the original document, you can use the "Original mode".

9. Place the flattened end of the engagement handle
(0) down through the slotted bracket beside the 
beam. Place shoulder bolt (A) through the bottom 
hole in engagement handle. Place rubber washer
(B) on shoulder bolt. Secure to bracket with lock
washer (C) and hex nut (D). See figure 7.
LEVER ON
PUMP
ENGAGEMENT
HANDLE
NOTCH
10. Place the engagement handle in the notch in the
slotted bracket (Reverse position). See figures 8 
and 11. Thread the ferrule (E) onto the end of 
engagement rod.
11. Push the lever on top of the pump as far toward
the rear of the unit as it will go as shown in figure
8. Hold it in this position and adjust the ferrule on 
the engagement rod so the ferrule lines up with the 
hole in the engagement handle.
12.
Secure the ferrule to engagement handle with
flat washer (G) and hairpin cotter (F).
FIGURES
OPERATION
FUNNEL
BEFORE STARTING
1.
Fill reservoir tank on log splitter with approx-
mately 2 gallons of Dexron II automatic trans
mission fluid as follows. Check oil level before 
each use.
A.
Block up front of log splitter so the beam is
level.
B.
Remove the oil check plug from the back of
the log splitter. See figure 9. If oil starts to 
come out of the hole, oil level is correct. If it 
does not, remove the cap from the breather 
tube and add oil until oil starts out of the 
check hole.
C.
Replace oil check plug. Replace cap on the
breather tube. Remove block from under
front of beam.
FIGURES