beautypg.com

NORAC UC4+BC+AP3 User Manual

Page 26

background image

23

6. Route C11 to the rear of the sprayer,

in the vicinity of the valve block.

7. Connect the 3-pin shroud (S3) on the

sense cable (C13) to the mating
connector (T3) on C11) (Figure 27).

8. Route the free end of C13 to the

Apache valve block and insert all of the
2-oin tees between the matching

Apache valve connections. For each
tee, the function (e.g. “Left Up”) is
labeled on the branch wire.

9. Connect the 6-pin shroud (S6) on the

main lift valve cable (C12) to the mating
connector (T6A) on C11 (Figure 27).

10. Route the free end of C12 to the

vicinity of the Apache main lift valve and
insert the 2-pin tees between the
matching Apache valve connections.

For each tee the function (e.g. “Main
Up”) is labeled on the branch wire.

11. Connect the 6-pin tower on the valve

cable (C3) onto the mating connector
(S6A) on C11 (Figure 27).

12. Route the free end of C3 to the vicinity

of the NORAC valve block.

13. The connectors on the valve cable

(C03) are marked RIGHT UP, LEFT
UP
, RIGHT DOWN and LEFT
DOWN
. Cables labeled with UP go
on the same side as the hydraulic hoses
on the 44963D block.

Figure 28: Valve Cable Connections

14. Connect the CAN Node cable (C02B)

to the 4-pin AMP plug on the tee of
C05 (Figure 29).

15. Connect the AMP 4-pin plug – P4 (C11)

to the 4-pin AMP receptacle on the tee
of C05 (Figure 29).

16. Route the sensor roll bias cable (C05)

to the chassis roll sensor. Follow
existing cables and/or hydraulic lines.

17. Route the CAN Node cable (C02B) to

the roll sensors. Follow existing cables
and/or hydraulic lines.

18. Connect the sensor branch cable (C02)

to the 4-pin AMP plug on C02B
(Figure 29).

19. Route the sensor branch cable (C02) to

the wing and main sensors. Follow
existing cables and/or hydraulic lines
along the boom.

20. Cable-tie the installed cables every 12

inches.