18. Connect the 2-pin connectors on the valve interface cable to the NORAC valve block, as

shown in Figure 23.

19. The connectors on the valve cable (C03) are marked RIGHT UP, LEFT UP, RIGHT DOWN

and LEFT DOWN. Cables labeled with UP go on the same side as the hydraulic hoses.

20. Connect the 3-pin tower on cable C19 to the 3-pin shroud on C17.

21. Route the free end of cable C19 to the 3rd station of the NORAC block and connect the 2-

pin DT connectors to the 3rd station block coils. The connector labeled Roll CW controls
the Main Up function and should be connected on the same side of the block as the hoses.

The connector labeled as Roll CCW controls the Main Down function.

Figure 23: Valve Cable Connections

22. Fasten the 8-way coupler (E11) to the boom with cable ties.

23. Connect P6 on C11, the chassis roll sensor (reference frame) and cable C07 to the 3-way

coupler (E10). Connect the free end of C07 to the 8-way coupler (E11).

24. Connect the boom frame roll sensor and intermediate frame roll sensor to the 8-way

coupler.

25. Connect the main lift sensor to the 8-way coupler using cable C07 and a 2-way coupler

(E12). Cable C07 and item E12 may not be needed if the 8-way coupler is mounted close
enough to the main lift sensor.

26. Connect two cables (C05) to the 8-way coupler and route along the booms to the wing

sensors. Follow existing cables and hoses to be sure the cable will not be pinched or
stretched.

27. At the sensor brackets, attach a 2-way coupler with terminator (E20) to the sprayer boom.

The 2-way coupler with terminator is the white two way coupler. Plug the sensor and the
CANbus cable into the 2-way coupler.

IMPORTANT:

Provide enough slack in all cables to account for the movement of the main
section, parallel lift, and FOLDING boom movement.