5| Electrical connection
5.1 Information for contactor and motor contactor selection
All	protection	devices	and	switching	or	monitoring	units	must	be	fitted	in	accordance	with	the	local	
safety	regulations	and	established	specifications	(e.g.	VDE)	as	well	as	with	the	manufacturer’s	infor-
mation. 
Motor protection switches are required! Motor contactors, feed lines, fuses and motor
protection switches must be rated on the basis of the maximum working current (see name plate). 
For motor protection use a current-dependent and time-delayed overload protection device for moni-
toring all three phases. Set the overload protection device so that it must be actuated within 2 hours, 
if there is 1.2 times the max. working current.
INFO
Connect the compressor motor in accordance with the circuit diagram 
(see inside of terminal box).
Use suitable cable entry point of the correct protection type (see
 name plate) for routing cables into the terminal box. Insert the strain 
 reliefs and prevent chafe marks on the cables.
Compare the voltage and frequency values with the data for the
 mains power supply. 
Only connect the motor if these values are the same.
DANGER
Risk	of	electric	shock!	High	voltage!	 
Only	carry	out	work	when	the	electrical	system	is	disconnected	
from the power supply!