4.5 Laying suction and pressure lines
4| Compressor assembly
4.4 Pipes
Pipes and system components must be clean and dry inside and free of scale, swarf and layers of
rust and phosphate. Only use air-tight parts.
Lay pipes correctly. Suitable vibration compensators must be provided to prevent pipes being
cracked and broken by severe vibrations.
 Ensure a proper oil return.
 Keep pressure losses to an absolute minimum.
Fig. 12
Rigid 
fixed point
As short as 
possible
A	rule	of	thumb:	Always	lay	the	first	pipe	section	starting	from	the	shut-off	valve	downwards
and parallel to the drive shaft.
ATTENTION Improperly installed pipes can cause cracks and tears, the result
being a loss of refrigerant.
INFO
Proper layout of the suction and discharge lines directly after 
the compressor is integral to the system’s smooth running and 
vibration behaviour. 
1
2
3
4
5
6
7
8
9
10
11
12
13
The
pipe connections have graduated inside diameters so that pipes with
standart millimetre and inch dimensions can be used.
The connection diameters of the shut-off valves are rated for maximum
compressor output.
The actual required pipe cross section must be
matched to the output. The same applies for non-return valves.
Fig. 11: graduated 
internal diameter