Windtura 750 maintenance instructions – Windy Nation Windtura 750 (No Slip Ring version) User Manual

Page 18

background image

18  

 

 

 

You  should  untwist  your  tower  wires  once  every  3-­‐4  months.  To  do  this  easily,  use  a  three  wire  

style  extension  cord.  Simply  unplug  the  three  prong  connector  (yellow  connector  in  the  figure  

above),  untwist  the  wire  and  plug  the  three  prong  connector  back  in.  Leave  about  3-­‐4  feet  of  

coiled  wire  which  allows  for  wire  slack  in  case  the  wires  get  twisted  in  the  tower.    

 

 
 
 
 
 

Windtura  750  Maintenance  Instructions  

 

(Warning:  Never  attempt  to  perform  maintenance  on  a  wind  turbine  on  a  windy  day.  Never  approach  

a  wind  turbine  when  the  blades  are  spinning.)  

Required  Maintenance  

Frequency  

Notes  

Grease  pivot  bar  

Once  a  year  

Steps  1  &  2  of  Figure  6  

Grease  tower  pipe  

Once  a  year  

Step  1a  of  Figure  3  

Inspect  blades  for  dents,  chips  

cracks.    

Clean  blades  of  any  dirt  or  

debris.  

Once  a  year  

Replace  blade(s)  if  structural  

integrity  is  compromised  

Inspect  all  fastener  

connections  

Once  a  year  

Tighten  fasteners  if  loose.  

Replace  fasteners  if  corrosion  

is  present  

Inspect  all  electrical  

connections  

Once  a  year  

Fix  or  replace  as  needed  if  

connection  is  bad  or  corrosion  

is  present  

Recommended  to  replace  750  

Watt  generator  bearings  

For  optimal  performance,  we  

suggest  to  replace  bearings  

every  7-­‐10  years.  

Car  mechanic  shops  are  

capable  of  replacing  bearings  

Check  tower  angle  is  vertical  

Twice  a  year  

Re-­‐align  tower  angle  when  

necessary