beautypg.com

Installing the furnace – Steffes DLF40B User Manual

Page 23

background image

22

Installing The Furnace

(cont'd) 

Peak  Control 

The heating elements in the furnace are controlled on­peak (not able to store heat in the brick core) via low 
voltage wiring. 

Connecting  the  furnace  to  load  control  signaling  device: 
Step  1
 

Route a low voltage circuit from the power company's load control peak signaling device to the 
charge control circuit board (30) located inside the electrical compartment of the furnace. 

Never  install  any  wiring  in  the  line  voltage  compartment  of  the  furnace  unless  it 
is  rated  for  line  voltage. 

Step  2 

Connect the field wiring to the BLUE and BLUE/WHITE wires hanging from the back of the charge 
control circuit board (30).  (See to the Low Voltage Wiring Diagram in this manual for a depictition 
of the location of these wires.) 

Step  3 

Be sure the "N.O./N.C." slide switch on the back of the charge control circuit board (30) is in the 
position that matches the input of the power company’s load control signaling device. 

N.O.  =  A closed power company switch will signal an off­peak time to the furnace (charging is 

enabled).  An open power company switch will signal an on­peak time to the furnace 
(charging is disabled). 

N.C.  =  An open power  company switch 

will signal an off­peak time to the 
furnace (charging is enabled).  A 
closed power company switch will 
signal an on­peak time to the 
furnace (charging is disabled). 

Optional  Features 

These  recommended  wiring  methods 
reflect  only  devices  that  accept  a  remote 
low  voltage  power  source.  Refer  to  the 
specific  installation  instructions  for  the 
device  before  making  any  connections  to 
the  furnace. 

Control  of  Other  Loads: 
The furnace can be used to control other loads in the 
application. To do so, connect the other loads using low 
voltage wire to the  “Y” positions of the terminal block 
located on the upper right front corner of the charge 
control circuit board.  (See the Low Voltage Diagram in 
the manual for reference to these terminal block posi­ 
tions.) 

Connecting  a  Humidifier: 
Figure 14 shows the general concept for connecting a 
humidifier to the furnace.  Refer to installation instructions 
of the humidifier prior to making any connections. 

Connecting  an  Electronic  Air  Filter: 
Figure 15 shows the general concept for connecting an 
electronic air filter to the furnace.  Refer to installation 
instructions of the filter prior to making any connections. 

NOTE 

FIGURE  14 

FIGURE  15 

NOTE

This manual is related to the following products: