superrr sunshine - 17
the dealer should
complete the following
assembly before the
customer receives
the cutter.
Step 6. attach the driveline to the output shaft of the cutter (1)
and to the PtO of the tractor.
Figure 3
Step 5. Before attaching to tractor, fill gearbox with 90 weight gear oil.
Remove top plug (1) to fill gear box. Remove 1/4" overflow plug (2).
When the oil level reaches the overflow plug, the gear box is full.
Figure 2
(Note: Failure to remove 1/4” overflow plug may cause overfilling that could
cause damage to the gearbox, i.e., seals.)
Figure 4
Figure 2
1
2
Figure 3
Step 7. cutting Height adjustment
to adjust cutting height up or down, remove bolts from tailwheel
adjustment bracket and move to preferred cutting height. Insert bolts,
lockwashers, nuts and tighten. Figure 4
aSSeMBly Section
1
Step 1 - Bolt the a-frame
(strut risers)(1) to the outside of
the top angle(2) using bolts(3), lock-
washers (4), and nuts (5). Do nuts tighten
until assembly is complete. Bolt lift pin (6)
through a-frame. Figure 1.
Step 2 - Insert bolt (9) through stiff-arm (8), through
outside of top rail (2), assemble with lockwasher (10) and nut (11). Do not tighten until assembly is
complete. Step 3 - Insert top bolt (7) through a-frame (1), through stiff-arm (8), through pivot-flex
(9) with spacer (13) insert in middle of pivot-flex, (other side) through stiff-arm (8), through a-frame
(1), and apply nut (14).
Step 4 - Begin tightening assembly. start with step 2, step 3, and then step 1.