Perimeter preparation, General perimeter preparation for the door frame – EFCO 5XP Series User Manual

Page 8

background image

EFCO CORPORATION 6/8/2012 PART NO. YW43

Page 8 of 34

5XP SLIDING GLASS DOOR INSTALLATION INSTRUCTIONS

Section II: General Perimeter Preparation for the Door Frame

A. Opening Condition Verification

1. The rough opening should be checked for the correct size as determined by frame size and

specified perimeter sealant joint widths listed in the architectural specifications and the shop
drawings. (See Fig. A)


2. Establish the face of the Sliding Glass Door line at the head, sill, and jambs. This reference

is arrived by using the architectural plans, general contractor’s reference lines, and shop
drawings.

3. Determine the high point of the masonry sill using string line or transit, and shim the sill

starter until level. (See Fig. B) To maintain a high level of resistance to water intrusion,
it is critical that the sill starter be level without twist or bow.

















Fig. A

Shim at Anchor
Locations

Fig. B

Note: For proper Sliding Glass Door operation
and drainage, it must be installed PLUMB and
LEVEL.

Plumb
Frame
and
Level