If the Point Row Option was ordered with the drill, the
hydraulics and drill electrical lead are factory-installed.
If the customer’s primary tractor is available, install the
control module in the tractor cable and make the electrical
connection. Consult the Point Row installation manual
provided.
If the primary tractor is not available, temporarily connect
the control module so that openers can be operated dur-
ing Setup.
Post Assembly Checklist
• Check that all working parts are moving freely, bolts are
tight, and cotter pins are spread.
• Check for proper tension and alignment on all drive
chains.
• Check that all safety decals and reflectors are located
correctly and are legible. Replace if improperly located
or damaged. Refer to “Safety Decals” in the Operator’s
manual.
• Inflate tires to recommended pressures as listed on the
“Tire Inflation Chart” on page 30. Tighten wheel bolts
as specified on “Torque Values Chart” on page 31.
Figure 15
Point-Row Connector