16. Unhook the drive-over ramp safety chains and lower the ramps to the
ground.
17. Lock the lid in either open or closed position, as required. Loosen thumb
screw on hinge to move lid and be sure to lock lid open during operation by
tightening thumb screw.
18. Remove and stow the jack. Refer to Figure 5.5 for drive over operating
position.
Figure 5.5 Operating Position
5.3.2. B
REAK
-I
N
P
ERIOD
& I
NITIAL
S
TART
-U
P
Your Portable Pit does not require an elaborate break-in. However, following a
few simple tips for the first 5 hours of operation can add to the reliability and life
of your machine.
• Follow the service schedule.
• Check hydraulic system oil level.
• Ensure that all hydraulic lines are free from damage, and that all fittings
are tight.
• Visually inspect the unit for damage to components. Replace or repair any
damaged or questionable parts.
• Check that all guards are installed, secured, and functioning as intended.
• Check the worksite and clean up the area, if needed.
• Regularly inspect the hydraulic motor mounting bolts for tightness (there
are 4 bolts).
• Inspect all hydraulic hoses, couplers, and fittings for tightness.
WARNING
Be sure to disable or lock out power source
before inspecting or servicing machine.