PC7 CONTROLLER OPERATION / MAINTENANCE MANUAL
4
MAINTENANCE
4.1 PREVENTIVE MAINTENANCE SCHEDULE
The following maintenance schedule is recommended to optimize pump
performance and minimize failures.
Adhering to the recommended preventative maintenance schedule along with
periodic inspection of the pump will ensure continued efficient operation and
overall reliable pump performance.
It is recommended that the Preventive Maintenance Record (Section 4.1.a) be
copied, maintained and kept with this unit for future reference.
PC7 Maintenance
Replacement Inspection
1 Year
2 Year
6 months
1 Year
2 Year
Component /
Comments
X
Fitting Nuts (Connections) P/N (9002914)
X
X
Detent Legs P/N (305-PD)
X
X
Shuttle Spool P/N (305-PJ)
X
X
Spring Bar P/N (305-QA)
X
Muffler Media (PC7 Controller) P/N (305-FR)