System Start Up Procedure
Fill canister water level to dip tube elbow.
**Valve and flange adapter not included and are available as an option only**
Pump isolation valves
Figure 2
Sensor assembly at any of
the locations on the pump.
Pressure Relief Valve
Must stay open during all purging processes.
WARNING:
During the purging process, the rate of flow is not equal. When air returns
to the canister you may see an overflow. You can control this by adjusting the flow back to
the canister by a valve. Pressure relief valve must remain open until all air is purged or the
canister may collapse. Do not completely seal the canister from outside air during this
process.
WARNING: