INSTALLATION

This includes:

1) Clocking the appliance to ensure the correct

fi ring rate (rate noted on label 41,500 Btu/h
(NG), after burning appliance for 15 minutes.

2) If required, adjusting the primary air to ensure

that the fl ame does not carbon. First allow the
unit to burn for 15-20 min. to stabilize.

CAUTION: Any alteration to the product that
causes sooting or carboning that results in dam-
age is not the responsibility of the manufacturer.

LOCATING YOUR

GAS FIREPLACE

A) Flat on Wall
B) Flat on Wall Corner
C) Recessed into Wall/Alcove
D) Corner

Diagram 1

1) When selecting a location for your fi replace,

ensure that the clearances are met.

2) The appliance must be installed on a fl at, solid,

continuous surface For example a wood, metal
or concrete fl oor or in a raised (on the wall) ap-
plication. The appliance must be installed on
a metal or wood panel extending the full width
and depth of the appliance.

3) The HZ54EPV Gas Fireplace can be installed

in a recessed position or framed out into the
room as in A, B, C and D.

See Diagram 1.

INSTALLATION

CHECKLIST

1) Locate appliance

a) Room location (Refer to "Locating Your Gas

fi replace" section)

b) Clearances to Combustibles (Refer to

"Clearances" section)

c) Mantle Clearances (Refer to "Mantel

Clearances" section)

d) Framing & Finishing Requirements (Refer

to "Framing & Finishing" section)

e) Venting Requirements (Refer to "Venting"

section)

f) Clearances to terminal

2) Make electrical connections for Power Vent

System and for unit. 120V power is required
to operate unit / power vent system.

3) Assemble Top and Side Standoffs (Refer to

"Unit Assembly Prior to Installation).


4) Slide unit into place.

5) Install vent (Refer to "Venting Arrangement"

sections).

7) Make gas connections (Refer to "Gas Line

Installation section).

8) Install 4 AA batteries into battery pack.

9) Test the pilot (Refer to "Pilot Adjustment"

section).

10) Test Gas Pressure (Refer to "Gas Pipe Pressure

Testing" section).

11) Install standard and optional features. Refer to

the following sections:

a)

Optional Log Set Installation

b) Glass Crystals/ Optional Ceramic
Stones

c)

Optional Firebox Base Pebbles

d) Optional

Refl ective Panels

e)

Faceplate / Door Frame Overlay

f) Remote

Control

g) Wall

Switch

12) Final check.

Before leaving this unit with the customer, the
installer must ensure that the appliance is fi ring
correctly and operation fully explained to
customer
.

4) This appliance is Listed for bedroom

installations using the standard Remote
(millivolt thermostat system). Some areas may
have further requirements, check local codes
before installation.

5) The HZ54EPV Direct Vent Gas Fireplace

is approved for alcove installations, see
"Clearances" section for details.

6) We recommend that you plan your installation

on paper using exact measurements for
clearances and fl oor protection before actually
installing this appliance. Have an authorized
inspector, dealer, or installer review your plans
before installation.

Note: For vent terminations refer to "Exterior

Vent Termination Locations" section.