MTS Criterion 60 - Lifting and Moving Instructions User Manual
Page 3

Lifting and Moving Instructions
MTS Criterion™ Series 60
Lifiting and Moving Instructions
3
Lifting and Moving Instructions
Contents
Moving the Load Unit to Its Final Location 6
Moving the Load Unit with a Forklift 9
Moving the Load Unit with an Overhead Crane 9
Moving the Integrated Operations Platform 12
Moving the Integrated Operations Platform to Its Final Location 12
Overview
To reliably and safely use the equipment, handle it according to the instructions.
Check for damages to the crate upon delivery. If you find any damage, contact
MTS as soon as possible and describe the details in the Commissioned Shipment
Receipt.
The load frame is heavy.
The load frame can seriously hurt you and damage your load frame.
Do not allow the load frame to drop or topple.
Make sure that your chains, slings, and crane have a working capacity greater
than the load frame’s weight (see the following table).
Make sure that the lifting hoist rings are tight.
Make sure that the crosshead locking bolts are fully tightened.
Lift the load frame only high enough to clear its pallet.
Operate the crane smoothly to prevent breaking shocks to the sling.
Note
The customer needs to supply equipment, such as hoist rings, straps
and wrenches before starting the process.
WARNING