7 troubleshooting, 7 troubleshooting -9, Manually propelled vertical lifts) -9 – JLG LSS Verticals Operator Manual User Manual
Page 17: Drivable vertical lifts) -9

SECTION 2 - SERVICE PROCEDURES - LOAD SENSING SYSTEM
3124289
– JLG Lift –
2-9
2.7 TROUBLESHOOTING
The following tables are furnished to provide possible res-
olutions for common Load Sensing System difficulties.
The wiring connectors and pins referenced in these trou-
bleshooting tables can be located on the electrical wiring
diagrams on the pages following these tables.
Table 2-4. Troubleshooting - Machine Indicates (Possible False) Platform Overload Condition -
(Manually Propelled Vertical Lifts)
Check For These Obvious Conditions First:
• Is the LSS platform mounting system secure and undamaged and all mounting arm joints working smoothly.
• Damaged or loose connectors or wires to LSS components.
STEP
ACTION
SPEC
YES
NO
1.
Is platform load at or below the maximum rated platform capacity?
See Capacity
Decal on Machine
Go to Step 2
Reduce Platform
Load
2.
Perform adjustment procedures (Section 2.2, LSS - Setup And
Adjustment). Reload platform to rated capacity, is system still indi-
cating an overload condition?
–
Go to Step 3
Done
3.
Set up and power machine on. Check voltage at Timing Module - J1
connector - Pin 3. Is voltage up to spec?
12V
Replace Timing
Module
Go to Step 4
4.
Check continuity between Timing Module J1 - Pin 3 and Pin 22 on
the Limit Switch. Is there continuity?
Go to Step 5
Repair or Replace
Wiring
5.
At the Limit Switch check voltage on Pin 21. Is voltage up to spec?
12V
Replace Limit
Switch
Go to Step 6
6.
At the Limit Switch, check Pin 21 connector for loose or damaged
condition. Is connector loose or damaged?
–
Repair or Replace
Connector
Replace Limit
Switch
Table 2-5. Troubleshooting - Machine Indicates (Possible False) Platform Overload Condition -
(Drivable Vertical Lifts)
Check For These Obvious Conditions First:
• Is the LSS platform mounting system secure and undamaged and all mounting arm joints working smoothly.
• Damaged or loose connectors or wires to LSS components.
STEP
ACTION
SPEC
YES
NO
1.
Is platform load at or below the maximum rated platform capacity?
See Capacity
Decal on Machine
Go to Step 2
Reduce Platform
Load